About the project
One of the team's largest mobilisations abroad: setting out, pile driving, tracker assembly, module installation, DC/AC cabling and commissioning support, on a large and hilly site.
Works carried out
- Setting out and pile driving
- Mounting structures
- Module installation
- DC/AC cabling
- Connections and commissioning
Project carried out by the SMACO team while working for a previous company.
The module count is estimated from the capacity (about 580 Wp per module); exact quantities come from the site reports.