Corbii Mari172 MW
Dâmbovița County, Romania2026In progress
172 MWbuilt by our team
130,200piles in our scope
338,520modules in our scope
6,714tables 2V26 + 2V13
2,441 kmDC solar cable (plot 4)
up to 155people on site at peak
About the project
Mechanical and electrical works on 172 MW of a fixed-tilt park. Pile driving went on through the winter. All figures below come from the daily site reports and the park layout.
Works carried out
- Setting out and pile driving
- Mounting structures
- Module installation
- DC/AC cabling
- Connections and commissioning
Project carried out by the SMACO team while working for a previous company.
Best day on site
1,016piles driven
5,732modules mounted
117tables assembled
102.7 kmDC cable laid